Commissioning progress at Kathleen Valley
11/07/2024Commissioning of the Kathleen Valley process plant is well underway.
The commissioning phase follows construction and entails all the activities, processes and checks required to ensure our plant is ready for operation. We’re verifying that all systems and components of the plant are installed correctly, operate as they should and can be maintained as needed.
The team are making steady progress to plan, working their way through an enormous 84 operable systems, 607 subsystems, ~4,000 function checks, ~400 drive tests and ~3,000 check sheets.
This animation shows you the major commissioning milestones which have been completed.
First production is coming soon and on schedule in mid-2024.